Twenty years into Nigeria’s financial investments to overhaul and upgrade the electricity sector, it has become apparent that stakeholders have rather pilfered the funds without providing electricity. Many projects under the Nigeria Integrated Power Project (NIPP) scheme, valued at about N2 trillion, have either been abandoned or stalled over the last two decades. The electricity megawatts they were expected to have added to the national grid were not delivered. The funds sunk into the projects have not been recovered. It is apparent that the problem of the power sector may not necessarily be the lack of financial investment by the government but sabotage by stakeholders who failed to execute power generation and distribution projects.
A recent report published by the Daily Trust exposed the magnitude of the sabotage. Under the NIPP project, funded from the Excess Crude Oil Account, the government projected to establish 10 gas-fired power stations with a combined installed capacity of 4,528.5 MW. With gas-powered power stations, Nigeria would not depend absolutely on annual rainfall to accumulate water in our dams for hydroelectric power generation. The country’s dependence on hydropower has been responsible for seasonal fluctuation in power supply when the water level in hydroelectric stations drops significantly. However, the gas-power stations did not generate power, more than two decades later. Some of them include the Egbema Power Plant in Imo State, the Gbarain Power Plant in Bayelsa, the Mambilla Power Plant in Taraba State, the Kukenda Power Station in Kaduna State, and the Okpai Independent Power Plant in Delta State. Additional investments in the Gurara II hydroelectric plant in Kaduna State and the Katsina Wind Farm Project failed to yield results.
Under the Transmission sector, as many as 334 projects funded since 2007 are yet to be completed, more than a decade after they were initiated. Unfortunately, the projects were funded through bilateral and multilateral facilities, debts that the government must service and repay. Apart from an investment of N125.2 billion by the government, loans were obtained from the World Bank, the Africa Development Bank, the French Development Agency (AFD), and the Japan International Cooperation Agency. The initial deadlines for completion of the projects have since elapsed. Though the government gave the contractors additional deadlines, they have also been missed. This failure at project management provides a clear insight into why the power sector has remained comatose and as a constant feature in political campaigns for over two decades now.
The Minister of Power, Adebayo Adelabu, was succinct when he lamented that the uncompleted projects were politically established and not necessarily meant to be executed to meet the electricity needs of the country. According to him, “We’ve committed the country’s money but are not getting the benefits of these investments. We’re not optimising such projects”.
Northerners have no moral right to reject Tinubu in 2027– Shehu Sani
Shehu Sani to Lamido: Look beyond politics on security issues
However, it is not enough for the minister to theorise about the problem. The authorities have failed to effectively supervise projects and hold the stakeholders who have received huge funding from the government to account. The implications are grim. The country’s capacity for power generation is put at 13,000 megawatts, but the daily distribution capacity is dismally 4,500 megawatts. This is in spite of the fact that Nigeria’s demand for electricity is very high. A significant portion of power needs is met by off-grid sources, such as diesel and petrol-powered generators, and solar power.
It is evident that the country is becoming a graveyard for failed power projects unless quick steps are taken to address the situation. We recommend that the government take an audit of the power projects to find out which among them could be revived, sustained, and completed. This step is critical because some of the projects initiated about two decades ago and abandoned may not be sustainable, and further funds channeled into them would be money into some sinkholes. The investigation should be thorough to include those who, through omission and commission, caused the failure of the projects. They must be prosecuted and the monies paid to them recovered.
The government must clean up the mess in the sector instead of approving the hike in electricity tariff. The problem with the sector is not exactly the tariff or even inadequate investment by the government. It is the failure of the government to monitor projects that have gulped a lot of funds but failed to produce electricity or those that failed to put in place the infrastructure to distribute energy that has been generated by power stations. Nigeria cannot continue to wallow under failed electricity projects. Power is very critical to households and industries; deliberate steps must be taken to correct past complacency and stakeholders who received funds from the government must be held accountable.
Disclaimer: The information contained in this content is for general purpose only and is generated from different sources other than MenBills Colony. Kindly report any fake news or false statement to support@menbills.com.ng
Hotspot
on I Don’t Regret Dumping Him”- Lady Dumps Her Husband After Sponsoring Her Abroad, Flaunts Her White Lover
16-01-2025 09:13:05am
Hotspot
on I Don’t Regret Dumping Him”- Lady Dumps Her Husband After Sponsoring Her Abroad, Flaunts Her White Lover
16-01-2025 09:12:27am
Musbau59
on Two soldiers, 6 villagers killed as suspected herders attack Benue community
13-01-2025 07:59:16am
Desire
on “He is a proper entertainer, love it” – Checkout top 10 dancing video of Osun governor Ademola Adeleke that will make your weekend (Video)
11-01-2025 10:32:19am
Samuel4
on ”It’s amazing how few years can make a difference in a persons life, congratulations to him” – Rapper Zlatan Ibile gifts himself a brand new customized Maybach van worth N375Million for his 30th birthday (Video)
18-12-2024 11:17:31am
tbabe28
on Mercy Aigbe loses home to fire outbreak
05-12-2024 02:44:40pm
Paramount72
on Husbands of female ministers suffer loneliness – Mike Bamiloye
29-11-2024 06:04:28pm
Samuel4
on ‘My wife was pregnant for another man inside marriage’
27-09-2024 04:43:01am
Ishiro
on ‘My wife was pregnant for another man inside marriage’
23-06-2024 11:38:24am
Ishiro
on ‘My wife was pregnant for another man inside marriage’
23-06-2024 11:38:14am
Oladunni
on ‘My wife was pregnant for another man inside marriage’
22-06-2024 04:19:58pm
Candy100
on Man who made allegations against E-Money and late Junior Pope’s wife publicly apologizes
22-06-2024 08:02:49am
Candy100
on BREAKING: Kano Govt Makes Fresh Announcement Over Emir Sanusi Amid Tussle In Kano
21-06-2024 08:15:39pm
Candy100
on 2027: Obi gives condition for merger with PDP
21-06-2024 08:10:14pm
Candy100
on Hajj: Last set of FCT pilgrims to report at camp today
21-06-2024 08:09:27pm